Worksheet

Budget Reconstruction Workbook

Rebuild a proposal budget line by line from stated assumptions, then compare your reconstruction against the headline total.

Type
Worksheet
Difficulty
Advanced
Time
90 min
Version
v1.0.0
Updated
8/9/2026
treasurybudgetsdata

What this helps you do

A headline total tells you almost nothing. Two proposals asking for the same amount can differ entirely in what the money buys and how much of it is contingency dressed as delivery.

This workbook reconstructs the budget from the ground up across personnel, contractors, infrastructure, marketing, professional services, travel, contingency and other costs, applies the stated token and FX assumptions, and puts your reconstruction beside the proposer figure so the variance is visible and explainable.

When to use this

  • A treasury request publishes a total you cannot trace to line items.
  • You want to know which categories drive the request before you question any of them.
  • You are comparing two proposals whose budgets are presented in different shapes.

When NOT to use this

  • The request is small enough that reconstruction costs more than it reveals.
  • No cost assumptions are published at all; ask for them first using the question tracker.
  • You are assessing delivery capability rather than cost; use the risk register.

What you'll need

  • The full budget breakdown as published
  • Stated headcount, rates, durations and unit costs
  • The ADA amount requested and any stated ADA price or FX assumption
  • The date the proposer priced the budget

Estimated completion time

90 minutes

Working time for one governance action, assuming the inputs listed here are already to hand.

How to use it

  1. 1Enter the proposer figure per category exactly as published, before you calculate anything.
  2. 2Rebuild each category from its own units: heads times rate times period, or unit cost times quantity.
  3. 3Where an assumption is missing, enter your own and label it clearly as your assumption.
  4. 4Record the ADA price and FX assumptions separately from the line items so they can be varied.
  5. 5Treat contingency as its own line, never spread through other categories.
  6. 6Calculate subtotals per category and a reconstructed total.
  7. 7Compare proposer total, reconstructed total, variance and variance percentage.
  8. 8Explain each material variance in one sentence: missing line, different assumption, or arithmetic error.
  9. 9Send unexplained variances to the question tracker rather than resolving them yourself.

The tool

Full worksheet - v1.0.0

Cost categories to reconstruct

  • Personnel: role, headcount, rate, period
  • Contractors: scope, day rate, days
  • Infrastructure: hosting, tooling, hardware
  • Marketing: channel, unit cost, volume
  • Professional services: legal, audit, accounting
  • Travel: trips, people, unit cost
  • Contingency: percentage and the base it applies to
  • Other costs, itemised rather than pooled

Assumption block

  • ADA amount requested
  • ADA price assumed by the proposer, and the date
  • ADA price you are using, and the date
  • Fiat currency of the underlying costs
  • FX rate assumed, and the source
  • Whether the request is denominated in ADA or in fiat

Comparison block

  • Proposer total per category
  • Reconstructed total per category
  • Variance in absolute terms
  • Variance as a percentage
  • Explanation for each material variance
  • Unexplained variance carried to the question tracker
Fictional Example

Invented for illustration. It does not describe a real governance action, proposal, or organisation.

Fictional reconstruction: Regional Developer Hubs pilot

  • Proposer total: 1,850,000 ADA at an assumed price of 0.55 USD
  • Personnel reconstructed: 4 staff, 12 months, 5,500 USD per month equals 264,000 USD
  • Infrastructure reconstructed: 3 sites, 2,400 USD per month equals 86,400 USD
  • Contingency stated at 10 percent, applied to a base the proposal does not define
  • Reconstructed total: 1,610,000 ADA at the same assumed price
  • Variance: 240,000 ADA, or 13 percent above the reconstruction
  • Explanation: contingency base undefined and a marketing line with no units
  • Both variances sent to the question tracker on 2026-08-07

How to interpret the result

  • A variance under roughly five percent usually reflects rounding and differing assumptions rather than a defect.
  • A variance you can explain is not a problem. A variance nobody can explain is the finding.
  • If the reconstruction comes out higher than the request, the proposal may be underfunded, which is its own delivery risk.
  • Categories where you had to invent assumptions show where disclosure is thin, regardless of the numbers.

Limitations

  • Reconstruction tests internal consistency, not whether the prices are reasonable in the market.
  • It depends on the assumptions the proposer published; thin disclosure produces a weak reconstruction.
  • ADA price movement between pricing date and enactment can dominate every line-item difference.

Sources and methodology

  • CIP-1694 treasury withdrawal actions

    Cardano Improvement Proposals

    Defines the treasury withdrawal mechanism this workbook reviews.

  • Cardano treasury and reserves data

    Placeholder entry. A canonical treasury data source has not been fixed for this edition.

    Canonical link not yet verified. Treat this entry as incomplete.

Learn this method

This tool records the work. The Training Lab teaches how to do it.

  • treasury-and-budget · Reading a Treasury Withdrawal Like an Operator

    Reading a Treasury Withdrawal Like an Operator

    Teaches how to reconstruct a budget from its stated assumptions.

    Open lesson
  • Lab lesson planned

    A dedicated lesson on budget reconstruction is planned.

Downloads

  • Markdown export: the complete tool, including metadata, instructions, the template, limitations, sources and version history.

No other file formats are published for this resource. We list a format only when the file exists.

Version and governance

Current version
v1.0.0
Published
8/9/2026
Last updated
8/9/2026
Next scheduled review
2/9/2027
Licence
CC BY 4.0
Editorial status
Not yet externally reviewed

No named reviewer is shown because no external review has been completed. Attribution appears only once a verified reviewer has signed off.

Changelog

  • v1.0.0 (2026-08-09) - First published edition.
Next in the workflow

Use these alongside it

The tools that usually come before or after this one.

WorksheetIntermediate60 min

Delivery-Risk Register

A structured register of the risks that could prevent a funded proposal from delivering what it promised, scored on probability and impact.

Workflow
Assess Delivery & Technical Risk
Formats
Markdown